PMI-SP · Question #308
The Define Activities process is the first process in the project time management knowledge are
The correct answer is D. Project document updates. Project document updates are not an output of the Define Activities process. Project document updates are the outputs for estimate activity resources. Project document updates include the Activity attributes Resource calendars Answer option A is incorrect. The activity list is…
Question
The Define Activities process is the first process in the project time management knowledge are
Options
- AActivity list
- BMilestone list
- CActivity attributes
- DProject document updates
How the community answered
(53 responses)- A4% (2)
- B6% (3)
- C2% (1)
- D89% (47)
Explanation
Project document updates are not an output of the Define Activities process. Project document updates are the outputs for estimate activity resources. Project document updates include the Activity attributes Resource calendars Answer option A is incorrect. The activity list is an output of the define activities process. Answer option C is incorrect. The activity attributes is an output of the define activities process. Answer option B is incorrect. The milestone list is an output of the define activities process.