The Define Activities process is the first process in the project time management knowledge are

The correct answer is D. Project document updates. Project document updates are not an output of the Define Activities process. Project document updates are the outputs for estimate activity resources. Project document updates include the Activity attributes Resource calendars Answer option A is incorrect. The activity list is…

Schedule Planning and Development

Question

The Define Activities process is the first process in the project time management knowledge are

Options

  • AActivity list
  • BMilestone list
  • CActivity attributes
  • DProject document updates

How the community answered

(53 responses)
  • A
    4% (2)
  • B
    6% (3)
  • C
    2% (1)
  • D
    89% (47)

Explanation

Project document updates are not an output of the Define Activities process. Project document updates are the outputs for estimate activity resources. Project document updates include the Activity attributes Resource calendars Answer option A is incorrect. The activity list is an output of the define activities process. Answer option C is incorrect. The activity attributes is an output of the define activities process. Answer option B is incorrect. The milestone list is an output of the define activities process.

Topics

#define activities#activity list#milestone list#process outputs