PMI-SP · Question #307
PMI-SP Question #307: Real Exam Question with Answer & Explanation
The correct answer is C. Fast track the project.. Fast tracking is a technique for compressing project schedule. In fast tracking, phases are overlapped that would normally be done in sequence. It is shortening the project schedule without reducing the project scope. It does not add any additional labor but it can introduce proj
Question
Options
- APerform resource leveling for the project.
- BCrash the project schedule.
- CFast track the project.
- DRemove things from the project scope.
Explanation
Fast tracking is a technique for compressing project schedule. In fast tracking, phases are overlapped that would normally be done in sequence. It is shortening the project schedule without reducing the project scope. It does not add any additional labor but it can introduce project risks. Answer option D is incorrect. Removing things from the project scope can reduce the project duration, but it will not satisfy the requirements the stakeholders have identified. Answer option A is incorrect. Resource leveling can actually increase the project duration. Answer option B is incorrect. Crashing can reduce the project duration but it increases the labor expense, something the stakeholders won't approve.
Community Discussion
No community discussion yet for this question.