nerdexam
PMI

PMI-SP · Question #309

PMI-SP Question #309: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #309. The question stem and answer options stay visible for context.

Question

Examine the figure given below: If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?

Exhibit

PMI-SP question #309 exhibit

Options

  • AThree days
  • BOne day
  • CFour days
  • DZero days

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PMI-SP Practice