PMI-SP · Question #309

Examine the figure given below: If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?

The correct answer is B. One day. Activity B is not on the critical path and it has a total of four days of float. If Activity B takes a total of eight days, it will consume three days of float. However, the total duration of the path ABEHJ may not exceed 26 days, as this is the total duration for the project…

Schedule Monitoring and Controlling

Question

Examine the figure given below:

If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?

Exhibit

PMI-SP question #309 exhibit

Options

  • AThree days
  • BOne day
  • CFour days
  • DZero days

How the community answered

(28 responses)
  • A
    7% (2)
  • B
    54% (15)
  • C
    25% (7)
  • D
    14% (4)

Explanation

Activity B is not on the critical path and it has a total of four days of float. If Activity B takes a total of eight days, it will consume three days of float. However, the total duration of the path ABEHJ may not exceed 26 days, as this is the total duration for the project. Although Activity H has a total of four days of float available, the consumption of three days of float on this path will reduce the total float for Activity H to just one day. If Activity H is delayed by more than one day, then the project will be late. Answer option D is incorrect. There is one day of float still available for Activity H. Answer options A and C are incorrect. These are not the valid answers, as there is just one day of float available

Topics

#float recalculation#network diagram#schedule impact analysis#critical path