nerdexam
PMI

PMI-SP · Question #278

PMI-SP Question #278: Real Exam Question with Answer & Explanation

The correct answer is D. Amount of buffer needed to the amount of buffer remaining. The difference between the buffer needed and the buffer remaining can determine whether corrective action is appropriate. Answer option C is incorrect. This is not an accurate description of how the critical chain determines the need for corrective action. Answer option B is inco

Question

You are the project manager of the GUH project. You are using the critical chain scheduling method as your approach to project scheduling. What two items can you compare in the critical chain method to determine if corrective action is appropriate?

Options

  • AAmount of buffer remaining to the amount of resources available
  • BAmount of buffer remaining to the amount of buffer used
  • CAvailability of project resources and project buffer
  • DAmount of buffer needed to the amount of buffer remaining

Explanation

The difference between the buffer needed and the buffer remaining can determine whether corrective action is appropriate. Answer option C is incorrect. This is not an accurate description of how the critical chain determines the need for corrective action. Answer option B is incorrect. This is not an accurate description of how the critical chain determines the need for corrective action. Answer option A is incorrect. This is not an accurate description of how the critical chain determines the need for corrective action.

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice