PMI-SP · Question #278
PMI-SP Question #278: Real Exam Question with Answer & Explanation
The correct answer is D. Amount of buffer needed to the amount of buffer remaining. The difference between the buffer needed and the buffer remaining can determine whether corrective action is appropriate. Answer option C is incorrect. This is not an accurate description of how the critical chain determines the need for corrective action. Answer option B is inco
Question
Options
- AAmount of buffer remaining to the amount of resources available
- BAmount of buffer remaining to the amount of buffer used
- CAvailability of project resources and project buffer
- DAmount of buffer needed to the amount of buffer remaining
Explanation
The difference between the buffer needed and the buffer remaining can determine whether corrective action is appropriate. Answer option C is incorrect. This is not an accurate description of how the critical chain determines the need for corrective action. Answer option B is incorrect. This is not an accurate description of how the critical chain determines the need for corrective action. Answer option A is incorrect. This is not an accurate description of how the critical chain determines the need for corrective action.
Community Discussion
No community discussion yet for this question.