PMI-SP · Question #300

What project management plan will document the time frame and frequency for the distribution of required information?

The correct answer is B. Communications Management Plan. The project's Communications Management Plan defines what information will be distributed, when it will be distributed, to whom it will be distributed, and the modality of the information. Answer option D is incorrect. The Schedule Management Plan defines the project work, when…

Stakeholder Communication

Question

What project management plan will document the time frame and frequency for the distribution of required information?

Options

  • AScope Management Plan
  • BCommunications Management Plan
  • CStakeholder Management Plan
  • DSchedule Management Plan

How the community answered

(34 responses)
  • A
    3% (1)
  • B
    94% (32)
  • C
    3% (1)

Explanation

The project's Communications Management Plan defines what information will be distributed, when it will be distributed, to whom it will be distributed, and the modality of the information. Answer option D is incorrect. The Schedule Management Plan defines the project work, when the project work will happen, resource utilization, and how the schedule will be monitored and Answer option C is incorrect. There is a stakeholder management strategy, but not a Stakeholder Management Plan. Answer option A is incorrect. The project's Scope Management Plan defines how the scope will be created, how the changes will be allowed, how the scope will be executed, monitored and controlled, and finally closed.

Topics

#communications management plan#information distribution#reporting frequency#schedule management