Which of the following are the outputs to the Determine Budget process? Each correct answer represents a complete solution. Choose all that apply.

The correct answer is A. Project document updates C. Cost performance baseline D. Project funding requirements. The outputs to the determine budget process are as follows: Cost performance baseline: The cost performance baseline is an authorized time-phased budget at completion. Project funding requirements: The project funding requirements are determined from total funding requirements…

Schedule Planning and Development

Question

Which of the following are the outputs to the Determine Budget process? Each correct answer represents a complete solution. Choose all that apply.

Options

  • AProject document updates
  • BScope baseline
  • CCost performance baseline
  • DProject funding requirements

How the community answered

(24 responses)
  • A
    92% (22)
  • B
    8% (2)

Explanation

The outputs to the determine budget process are as follows: Cost performance baseline: The cost performance baseline is an authorized time-phased budget at completion. Project funding requirements: The project funding requirements are determined from total funding requirements and periodic funding requirements. Project document updates: The project document updates consists of risk register, cost estimates and project schedule. Answer option B is incorrect. Scope baseline is an input to the determine budget process.

Topics

#determine budget#cost performance baseline#project funding requirements#process outputs