nerdexam
PMI

PMI-SP · Question #275

You are creating a status report to show how your project is progressing. Management is interested in several key activities and their status. You need to report work performance information to…

The correct answer is B. Performance of the selected project vendors. Vendor performance, while important, is not part of the work performance information. Management is interested in the how well the project is performing, what activities are currently underway, and what's been completed to date. Answer option A is incorrect the project's…

Schedule Monitoring and Controlling

Question

You are creating a status report to show how your project is progressing. Management is interested in several key activities and their status. You need to report work performance information to management. All of the following are example of work performance information you should include in your report except for which one?

Options

  • AHow the project is performing on its schedule.
  • BPerformance of the selected project vendors
  • CWhich activities have been started and which activities have been finished.
  • DPercent of completion for the in-progress activities

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    91% (20)
  • C
    5% (1)

Explanation

Vendor performance, while important, is not part of the work performance information. Management is interested in the how well the project is performing, what activities are currently underway, and what's been completed to date. Answer option A is incorrect the project's performance on schedule should be reported Answer option C is incorrect as management is interested in what activities have been started and Answer option D is incorrect as management does want to know the percent of completion for the in-progress activities

Topics

#work performance information#status reporting#schedule monitoring#performance reporting

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice