nerdexam
PMI

PMI-SP · Question #296

PMI-SP Question #296: Real Exam Question with Answer & Explanation

See the full explanation below for the reasoning.

Question

Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below: If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?

Exhibit

PMI-SP question #296 exhibit

Options

  • AThe project will complete on time.
  • BThe project will be late by one day.
  • CThe project will be late by two days.
  • DThe project will be early by two days.

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice