nerdexam
PMI

PMI-SP · Question #296

Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's…

You've hit your limit · resets 5am (America/New_York)

Schedule Monitoring and Controlling

Question

Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:

If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?

Exhibit

PMI-SP question #296 exhibit

Options

  • AThe project will complete on time.
  • BThe project will be late by one day.
  • CThe project will be late by two days.
  • DThe project will be early by two days.

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#critical path#network diagram#schedule impact#float analysis

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice