PMI-SP · Question #295
PMI-SP Question #295: Real Exam Question with Answer & Explanation
The correct answer is A. Risk activities. Risk activities are not part of the schedule data. Risk is documented in the risk register, and monitored and controlled throughout the project. In some instances, risk may be part of the activity attributes. The schedule data includes the schedule milestones, schedule activities
Question
Options
- ARisk activities
- BSchedule activities
- CActivity attributes
- DSchedule milestones
Explanation
Risk activities are not part of the schedule data. Risk is documented in the risk register, and monitored and controlled throughout the project. In some instances, risk may be part of the activity attributes. The schedule data includes the schedule milestones, schedule activities, activity attributes, and the assumptions and constraints. The schedule data includes the schedule activities, schedule milestones, activity attributes, and documentation of all known assumptions and constraints. The sum of additional data varies by application area. The schedule data commonly supplied as supporting details includes: Resource requirement by time period, frequently in the category of histogram Alternative schedules, such as best case or worst case, or resource leveled, with or without imposed dates Scheduling of contingency reserves Answer option D is incorrect. Schedule milestones are part of the schedule data. a Answer option B is incorrect. Schedule activities are part of the schedule data. Answer option C is incorrect. Activity attributes are part of the schedule data.
Community Discussion
No community discussion yet for this question.