PMI-SP Exam Questions
328 real PMI-SP exam questions with expert-verified answers and explanations. Page 7 of 7.
- Question #321
John works as a Project Manager for Blue Well Inc. He is measuring cost efficiency of his project. The key values are provided in the table below: What is the cost performance inde...
- Question #322
Ben is the project manager of the NHF Project for his organization. Some delays early in the project have caused the project schedule to slip by nearly 15 percent. Management would...
- Question #323
Laura is the project manager for her organization and management has requested her to create a report on her project's performance. Laura needs to analyze her current project perfo...
- Question #324
Which of the following documents captures and defines the work activities, deliverables, and a timeline that a vendor will execute against in performance of work for a customer?
- Question #325
A construction company is about to start a new project. It requires hiring a project manager for this project. Which of the following are the most important skills that a person mu...
- Question #326
Which of the following individuals has a management role in a core business area, such as research and development, design, manufacturing, provisioning, testing, or maintenance?
- Question #327
John is the project manager for his organization. He has created a status dashboard for his stakeholders. What is a status dashboard?
- Question #328
Which of the following statements is true regarding schedule variances?
- Question #329
In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.
- Question #330
You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third...
- Question #331
You are a project manager for a documentary film company. In light of a recent regional tragedy, the company president wants to get a new documentary on the rescue efforts of the h...
- Question #332
A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has bee...
- Question #333
How is scheduled variance calculated using the earned value technique?
- Question #334
Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort. What is discrete...
- Question #335
Lily works as a project manager for BlueWell Inc. She has recorded the following duration estimates for an activity in her project: optimistic 35, most likely 50, and pessimistic 9...
- Question #336
Nancy is the project manager of the JJJ Project. This project has recently been approved by the project customer as complete so Nancy must now finalize the administrative closure....
- Question #337
You are the project manager of the AHQ project. This project is scheduled to last for six months and will require $345,000 to complete. If the project completes earlier than schedu...
- Question #338
Harry works as a project manager for the NHQ project. His project has a budget of $2,208,456 and is scheduled to last for three years. His project is currently forty percent comple...
- Question #339
You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below: Measureme...
- Question #340
Kenny is the project manager for the NHQ organization. She is creating the project duration estimates. She has stressed to her project team that they will need to create accurate a...
- Question #341
John is the project manager for the ABC project. He is finalizing the budget of the project. He is concerned about the direct costs involved in the project. Which of the following...
- Question #342
Which of the following group activity techniques allows a large number of ideas to be sorted into groups for review and analysis?
- Question #343
Which of the following techniques is used to perform progressive elaboration planning where the work to be accomplished in the near future is planned in detail at a low level of th...
- Question #344
You're a project manager and you've completed your project schedule. The schedule will take 18 months to complete the project work. Throughout the schedule there are instances that...
- Question #345
A project team installs 2,500 light fixtures in a new office building, and each light fixture takes one hour to install. The project manager can predict that it will take 2,500 hou...
- Question #346
Andy is the project manager for his project. Andy and his project team are identifying stakeholders who can significantly impact the project, what the level of participation for ea...
- Question #347
You are the project manager of the NHQ project. Your project has a budget of $1,258456 and is scheduled to last for three years. Your project is currently forty percent complete th...
- Question #348
You work as a Project Manager for Tech Perfect Inc. Several projects are running under your supervision. Martha, the team leader of a project, provides you performance indexes of h...