PMI-SP · Question #323
Laura is the project manager for her organization and management has requested her to create a report on her project's performance. Laura needs to analyze her current project performance and then…
The correct answer is C. Performance measurement baseline. The performance measurement baseline, which can be comprised of cost, scope, and schedule, is the foundation for creating a performance report. Answer option B is incorrect. The scope baseline will only reflect the performance of the scope, whereas performance reports typically…
Question
Laura is the project manager for her organization and management has requested her to create a report on her project's performance. Laura needs to analyze her current project performance and then compare it against what, in order to create a performance report?
Options
- ACost variances and Cost Performance Index
- BScope baseline
- CPerformance measurement baseline
- DSchedule variances, planned value, and the Schedule Performance Index
How the community answered
(18 responses)- A6% (1)
- C89% (16)
- D6% (1)
Explanation
The performance measurement baseline, which can be comprised of cost, scope, and schedule, is the foundation for creating a performance report. Answer option B is incorrect. The scope baseline will only reflect the performance of the scope, whereas performance reports typically need scope, time, and cost as its foundation. Answer option A is incorrect. Cost variances and the cost performance index are cost values that must be considered along with the scope performance and schedule performance. Answer option D is incorrect. Only reporting performance on the schedule is not enough for a performance report. Laura should also report on scope and cost at a minimum.
Topics