PMI-SP · Question #329
In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.
The correct answer is A. Increase, increase. You've hit your limit · resets 5am (America/New_York)
Schedule Planning and Development
Question
In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.
Options
- AIncrease, increase
- BDecrease, decrease.
- CIncrease, decrease.
- DIncrease, increase or decrease.
- EDecrease, increase.
How the community answered
(51 responses)- A94% (48)
- B2% (1)
- E4% (2)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#resource smoothing#resource leveling#schedule duration#project costs