nerdexam
PMI

PMI-SP · Question #329

In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.

The correct answer is A. Increase, increase. You've hit your limit · resets 5am (America/New_York)

Schedule Planning and Development

Question

In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.

Options

  • AIncrease, increase
  • BDecrease, decrease.
  • CIncrease, decrease.
  • DIncrease, increase or decrease.
  • EDecrease, increase.

How the community answered

(51 responses)
  • A
    94% (48)
  • B
    2% (1)
  • E
    4% (2)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#resource smoothing#resource leveling#schedule duration#project costs

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice