nerdexam
PMI

PMI-SP · Question #315

Winnie is the project manager for her company. She has been recording the actual durations of the project work to determine the actual progress of her project. Winnie needs to generate an updated…

The correct answer is C. Scheduling tool. Answer option A is incorrect. The critical path method can be analyzed, but it is a part of the project management information system. In addition, the critical path is not better or worse than the critical chain method so by having both answers among the choices both answers…

Schedule Planning and Development

Question

Winnie is the project manager for her company. She has been recording the actual durations of the project work to determine the actual progress of her project. Winnie needs to generate an updated project schedule based on project performance. She is using the supporting schedule data, manual scheduling methods, and her project management software to perform schedule network analysis. What other tool Winnie can use to help and generate an updated project schedule?

Options

  • ACritical path method
  • BSchedule management plan
  • CScheduling tool
  • DCritical chain method

How the community answered

(35 responses)
  • B
    3% (1)
  • C
    94% (33)
  • D
    3% (1)

Explanation

Answer option A is incorrect. The critical path method can be analyzed, but it is a part of the project management information system. In addition, the critical path is not better or worse than the critical chain method so by having both answers among the choices both answers are Answer option D is incorrect. The critical chain method can be analyzed, but it is the part of the project management information system. In addition, the critical path is not better or worse than the critical path method so by having both answers among the choices both answers are Answer option B is incorrect. The schedule management plan may need to be referenced to create a new project schedule, but it is not a tool that Winnie can use.

Topics

#schedule network analysis#scheduling tool#schedule development#project management software

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice