PMI-SP · Question #346
Andy is the project manager for his project. Andy and his project team are identifying stakeholders who can significantly impact the project, what the level of participation for each identified…
The correct answer is D. Stakeholder management strategy. Andy and his project team are creating the stakeholder management strategy. The goal is to identify a method to gain support through communications for the project. The stakeholder management strategy is an approach to raise the support and decrease negative impacts of…
Question
Andy is the project manager for his project. Andy and his project team are identifying stakeholders who can significantly impact the project, what the level of participation for each identified stakeholder may be, and classifying the stakeholders by common characteristics, concerns, and their perception of the project. Andy and his project team want to define an approach as a result of this information to gain support from the stakeholders for their project. What should Andy and his project team create in this scenario?
Options
- AStakeholder assessment information
- BStakeholder register
- CCommunications management plan
- DStakeholder management strategy
How the community answered
(21 responses)- A10% (2)
- B5% (1)
- C5% (1)
- D81% (17)
Explanation
Andy and his project team are creating the stakeholder management strategy. The goal is to identify a method to gain support through communications for the project. The stakeholder management strategy is an approach to raise the support and decrease negative impacts of stakeholders during the complete project life cycle. It consists of the following essential elements: Key stakeholders who can significantly impact the project Level of participation in the project desired for each identified stakeholder Stakeholder groups and their management Answer option B is incorrect. The stakeholder register contains the stakeholder's identification information, assessment information, and stakeholder classification, but not the management strategy. Answer option A is incorrect. Stakeholder assessment information is part of the stakeholder Answer option C is incorrect. The communications management plan defines how and when communication will happen.