PMI-SP · Question #347
PMI-SP Question #347: Real Exam Question with Answer & Explanation
The correct answer is D. -$54,044. The variance at completion can be found by subtracting the estimate at completion from the budget at completion. In this instance, it is: Variance at completion = EAC - BAC = $1,258,456 - $1,312,500. Answer option C is incorrect. You can calculate the variance at completion. Answ
Question
Options
- A-$21,618
- B-$62,922
- CZero - you would not know what this will cost until the project is complete.
- D-$54,044
Explanation
The variance at completion can be found by subtracting the estimate at completion from the budget at completion. In this instance, it is: Variance at completion = EAC - BAC = $1,258,456 - $1,312,500. Answer option C is incorrect. You can calculate the variance at completion. Answer option A is incorrect. This is the cost variance for the project. Answer option B is incorrect. This is the schedule variance for the project.
Community Discussion
No community discussion yet for this question.