nerdexam
PMI

PMI-SP · Question #313

Holly is the project manager of her project. She has chosen to crash the project due to time constraints that have been imposed on her project. When Holly crashes the project what project document…

The correct answer is D. Activity attributes. When Holly adds resources to the project, as in this instance, she will need to update the activity attributes to reflect the new labor. Activity attributes are an output of the Define Activity process. These attributes refer to the multiple components that frame up an…

Schedule Monitoring and Controlling

Question

Holly is the project manager of her project. She has chosen to crash the project due to time constraints that have been imposed on her project. When Holly crashes the project what project document must be updated to reflect this change to the approach?

Options

  • ADevelop schedule process
  • BRisk register
  • CProject risk management plan
  • DActivity attributes

How the community answered

(19 responses)
  • B
    5% (1)
  • D
    95% (18)

Explanation

When Holly adds resources to the project, as in this instance, she will need to update the activity attributes to reflect the new labor. Activity attributes are an output of the Define Activity process. These attributes refer to the multiple components that frame up an activity. The components for each activity during the early stages of the project are the Activity ID, WBS ID, and Activity name. At the later stages, the activity attributes include Activity codes, Predecessor activity, activity description, logical relationship, successor activity, leads and lags, imposed dates, and constraints and assumptions. Activity attributes are used for schedule development and for ordering, selecting, and sorting the planned schedule activities in a number of ways within reports. In project document updates, activity attributes are updated to include any revised resource requirements and other revision generated by the develop schedule process.

Topics

#crashing#schedule compression#activity attributes#schedule updates

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice