PMI-SP · Question #273
Adrian is the project manager for her project. This new project needs to identify all the stakeholders that will be affected by the project's outcome. How stakeholders are usually identified?
The correct answer is D. Stakeholders are usually identified by interviewing identified stakeholders and expanding the. Stakeholders are interviewed and can help identify other stakeholders that should be included in the project communications. Answer option B is incorrect. According to the PMBOK, this is not the best answer. Answer option A is incorrect. Stakeholders are entered into a…
Question
Adrian is the project manager for her project. This new project needs to identify all the stakeholders that will be affected by the project's outcome. How stakeholders are usually identified?
Options
- AStakeholders are usually identified through a stakeholder register.
- BStakeholders are identified by the project team, project sponsor, and management.
- CStakeholders are identified through the project customers.
- DStakeholders are usually identified by interviewing identified stakeholders and expanding the
How the community answered
(47 responses)- A2% (1)
- C4% (2)
- D94% (44)
Explanation
Stakeholders are interviewed and can help identify other stakeholders that should be included in the project communications. Answer option B is incorrect. According to the PMBOK, this is not the best answer. Answer option A is incorrect. Stakeholders are entered into a stakeholder register, not identified by it. Answer option C is incorrect. Project customers are stakeholders.
Topics
Community Discussion
No community discussion yet for this question.