The correct answer is C. To help the project team understand what work is required to be completed. The primary reason for including the activity identifier and the scope of work description for each activity is to ensure the project team understands what work is required to be completed. Answer option B is incorrect. Profit and loss statements are not required for all projects

Question

You are the project manager for the NQQ Project for your organization. You and the project team are creating the activity list for the NQQ Project. You have instructed the project team members that they should include an activity identifier and a scope of work description for each activity in the activity list. Why is this information needed?

Options

  • ATo track the work to the project requirements
  • BTo maintain profit and loss statements for the project
  • CTo help the project team understand what work is required to be completed
  • DTo communicate the work to be completed to the project stakeholders

Explanation

The primary reason for including the activity identifier and the scope of work description for each activity is to ensure the project team understands what work is required to be completed. Answer option B is incorrect. Profit and loss statements are not required for all projects and they are linked to actual performance against a project baseline. Answer option D is incorrect. Communicating to the stakeholders is always a good idea, but stakeholders would not usually need to know the activity details. Their focus is on project benefits and deliverables. Answer option A is incorrect. A requirements traceability matrix is the tool to link requirements to project deliverables.