- Question #201
A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The b...
- Question #202
A daily standup Scrum meeting is BEST accomplished in a:
- Question #203
A new stakeholder has requested the status and progress reports for the project milestones. Which of the following documents should the project manager address FIRST?
- Question #204
When an action is taken on a risk, which of the following is being done and which document needs to be updated?
- Question #205
A project schedule lists a resource as 50% because it likely:
- Question #206
A project manager is mapping qualifications and available personnel to the project requirements. Which of the following activities is the project manager completing?
- Question #207
Which of the following is a reason for assessing risk in a project?
- Question #208
The project sponsor wishes to implement a 24/7 solution for the service desk, requiring the establishment of the capability on three different continents. Which of the following fa...
- Question #209
A project team is defining detailed risks. Which of the following project phases is taking place?
- Question #210
Which of the following statements are correct regarding project management? (Select two.)
- Question #211
A client has provided a list of deliverables to include in the project scope. Which of the following will allow the project team to ensure all deliverables are included in the fina...
- Question #212
A minor change to the baseline schedule is required. This change will be the second minor modification to the schedule. Which of the following is the appropriate version number?
- Question #213
Which of the following is used to perform a root cause analysis?
- Question #214
Which of the following documents is typically signed by the vendor and includes a reference for how customers' internal information will be protected?
- Question #215
A project has fallen behind schedule for no obvious reason, so the PM has gathered the team to brainstorm. Which of the following should the PM do NEXT?
- Question #216
A project sponsor wants to demonstrate progress on a deliverable to all stakeholders at the next tollgate meeting. This feature was not scheduled for this tollgate, but the project...
- Question #217
A vendor was removed from a company due to non-performance but continues to submit invoices for work that was not completed. Which of the following should the project manager do to...
- Question #218
During the storming stage of a project team's development, it is common to experience confusion about tasks and responsibilities because:
- Question #219
A project manager procures additional resources from a local company. Which of the following- describes this event?
- Question #220
In which of the following situations is a project manager MOST likely to use a process diagram?
- Question #221
A project has passed a phase-gate, and the new phase is ready to begin. Which of the following is the MOST appropriate method to communicate the transition to team?
- Question #222
A project manager receives a call from the area regional building department and is informed that, upon inspection, waterlines from public water access to the project building do n...
- Question #223
A project manager at a projectized organization is finishing the objective goals for the appraisal process. Performance goals have been identified for colocated individuals working...
- Question #224
During the testing phase, a team member has informed the project manager that the test environment was set with inadequate client information, putting the project in jeopardy. Whic...
- Question #225
A subcontractor has submitted design documentation on the deliverable due date, but it will require rework. The activity is on the critical path of the project schedule. Which of t...
- Question #226
A project manager must create documentation before the project kickoff meeting. Which of the following documents will identify the project, introduce the project manager, and estab...
- Question #227
Which of the following are mutually binding project documents? (Select two.)
- Question #228
An organization has determined that all projects must use a remote dashboard to allow portfolio management. Which of the following would enforce this directive?
- Question #229
A project team has failed to deliver on changes the project manager outlined on a call two weeks ago. The project team members indicate they did not remember the contents on the ca...
- Question #230
A quality auditor finds suspicious code during a software test. For which of the following could this be a trigger?
- Question #231
A project manager wants to ensure that a detailed overview of a new kitchen fits the client's standards. Which of the following will the project manager MOST likely work to accompl...
- Question #232
A key stakeholder asks the project manager for additional features. Which of the following documents should the project manager refer to before responding to this request?
- Question #233
Which of the following risk strategies prevents a risk from impacting a project?
- Question #234
An active project has a CPI of 0.92. Which of the following can be determined?
- Question #235
A project team completed a brainstorming activity to determine potential issues with a project. Which of the following activities should the project team do NEXT?
- Question #236
A customer has stated that meeting the project schedule and milestones takes priority and is, therefore, willing to spend additional funds to sustain operations. The project team m...
- Question #237
While developing a project schedule, the project manager is attempting to sequence the following tasks: Which of the following is the correct sequence for the above tasks?
- Question #238
Which of the following represents additional unauthorized requirements from the client?
- Question #239
A contract review meeting has been scheduled with a non-performing vendor. The project manager has been asked to provide recommendations for continuous service improvements and rem...
- Question #240
Which of the following describes KPIs?
- Question #241
Before a team can start on a sprint, they will need to:
- Question #242
A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project...
- Question #243
Which of the following is the MOST appropriate communication method for a highly confidential message to a Multilanguage global project team?
- Question #244
Which of the following defines the minimum level of engagement of a stakeholder?
- Question #245
At a project kickoff meeting, several team members acted unprofessionally. The project manager would like to set expectations for team interaction. Which of the following would BES...
- Question #246
A company is in the process of combining the human resources and marketing departments. Which of the following describes this change?
- Question #247
A change is being implemented on a project, and while in testing, it becomes clear that the change cannot be finalized due to the severe impact it would have on other critical syst...
- Question #248
During a project, which of the following shows when risks should be reassessed?
- Question #249
A project has 45 lines of communication. Which of the following shows how many stakeholders does the project have?
- Question #250
A status report shows that the earned value is $50,000, the planned value is $40,000, and actual costs are $45,000. Which of the following is the SPI of the project, and is the pro...