A project team completed a brainstorming activity to determine potential issues with a project. Which of the following activities should the project team do NEXT?

The correct answer is A. Risk identification. Brainstorming is a technique used within risk identification, so after completing a brainstorm the team must formalize results through the risk identification process before moving forward.

Project management concepts

Question

A project team completed a brainstorming activity to determine potential issues with a project. Which of the following activities should the project team do NEXT?

Options

  • ARisk identification
  • BRisk quantification
  • CRisk planning
  • DRisk response

How the community answered

(32 responses)
  • A
    91% (29)
  • B
    3% (1)
  • C
    6% (2)

Why each option

Brainstorming is a technique used within risk identification, so after completing a brainstorm the team must formalize results through the risk identification process before moving forward.

ARisk identificationCorrect

Brainstorming is one input technique within the risk identification process, not a separate preceding step; after generating a raw list of potential issues through brainstorming, the team must complete risk identification by formally documenting, categorizing, and recording those issues in the risk register. Risk identification must be fully completed before the team can proceed to quantification, response planning, or other downstream risk activities.

BRisk quantification

Risk quantification assigns probability and impact values to identified risks and can only occur after risks have been formally identified and documented in the risk register.

CRisk planning

Risk planning defines the overall approach and methodology for managing risks and is typically performed earlier in the project lifecycle, before identification activities begin.

DRisk response

Risk response develops strategies to address analyzed risks and is a later step that requires both completed identification and analysis as inputs.

Concept tested: Risk identification process and brainstorming as an elicitation technique

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#risk identification#risk management process#brainstorming#risk planning

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice