A customer has stated that meeting the project schedule and milestones takes priority and is, therefore, willing to spend additional funds to sustain operations. The project team must ensure completion of the:
Options
- Abusiness continuity plan.
- Bincident response plan.
- Cdisaster recovery plan.
- Drisk management plan.
- Equality management plan.