A project team is defining detailed risks. Which of the following project phases is taking place?

The correct answer is D. Planning. High level risk are in the Initiation stage, detailed risks are in the Planning Stage.

Project life cycle phases

Question

A project team is defining detailed risks. Which of the following project phases is taking place?

Options

  • AInitiation
  • BMonitor and control
  • CExecution
  • DPlanning

How the community answered

(32 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    3% (1)
  • D
    88% (28)

Explanation

High level risk are in the Initiation stage, detailed risks are in the Planning Stage.

Topics

#project phases#planning phase#risk identification#project life cycle