A project team is defining detailed risks. Which of the following project phases is taking place?
The correct answer is D. Planning. High level risk are in the Initiation stage, detailed risks are in the Planning Stage.
Project life cycle phases
Question
A project team is defining detailed risks. Which of the following project phases is taking place?
Options
- AInitiation
- BMonitor and control
- CExecution
- DPlanning
How the community answered
(32 responses)- A6% (2)
- B3% (1)
- C3% (1)
- D88% (28)
Explanation
High level risk are in the Initiation stage, detailed risks are in the Planning Stage.