CompTIA
PK0-004 · Question #208
The project sponsor wishes to implement a 24/7 solution for the service desk, requiring the establishment of the capability on three different continents. Which of the following factors is MOST…
The correct answer is C. Time zones and language barriers. Time-zone and expansion of resource across 3 continents has nothing to do with level of confidentiality.
Project management concepts
Question
The project sponsor wishes to implement a 24/7 solution for the service desk, requiring the establishment of the capability on three different continents. Which of the following factors is MOST likely to influence communication methods across the project?
Options
- APersonal preferences and message content
- BLevel of message/report detail and confidentiality constraints
- CTime zones and language barriers
- DTechnological and criticality factors
How the community answered
(27 responses)- A4% (1)
- C93% (25)
- D4% (1)
Explanation
Time-zone and expansion of resource across 3 continents has nothing to do with level of confidentiality.
Topics
#communication methods#global teams#time zones#language barriers