nerdexam
CompTIA

PK0-004 · Question #218

During the storming stage of a project team's development, it is common to experience confusion about tasks and responsibilities because:

The correct answer is B. there is a lack of trust among team members. The storming stage of Tuckman's team development model is characterized by interpersonal conflict and a lack of trust as team members compete for roles and challenge authority. This distrust directly causes confusion about tasks and responsibilities.

Project management concepts

Question

During the storming stage of a project team's development, it is common to experience confusion about tasks and responsibilities because:

Exhibit

PK0-004 question #218 exhibit

Options

  • Athere is unfamiliarity with the project structure.
  • Bthere is a lack of trust among team members.
  • Cthere are minimal team decisions.
  • Dthere is no engagement of the team by the project manager.

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    93% (26)
  • C
    4% (1)

Why each option

The storming stage of Tuckman's team development model is characterized by interpersonal conflict and a lack of trust as team members compete for roles and challenge authority. This distrust directly causes confusion about tasks and responsibilities.

Athere is unfamiliarity with the project structure.

Unfamiliarity with the project structure is characteristic of the forming stage, not the storming stage, where the team has already been introduced to the project.

Bthere is a lack of trust among team members.Correct

In the storming stage of Tuckman's model, team members begin to push against boundaries and compete for influence, which creates an environment of low trust. This lack of trust leads to unclear communication, role conflicts, and confusion about who is responsible for what. The distrust is the root cause of the dysfunction in this stage, distinguishing it from the forming stage where unfamiliarity is the primary issue.

Cthere are minimal team decisions.

Minimal team decisions describes a passive team dynamic more associated with forming or a dysfunctional team, not the conflict-driven storming stage.

Dthere is no engagement of the team by the project manager.

Lack of PM engagement is a management failure, not a defining characteristic of the storming stage, which occurs regardless of PM involvement.

Concept tested: Tuckman team development storming stage characteristics

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#team development#Tuckman model#storming stage#team dynamics

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice