nerdexam
ExamsPK0-004Questions#201
CompTIA

PK0-004 · Question #201

PK0-004 Question #201: Real Exam Question with Answer & Explanation

Sign in or unlock PK0-004 to reveal the answer and full explanation for question #201. The question stem and answer options stay visible for context.

Question

A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000. Which of the following represents the cost variance for both project completions?

Options

  • A-$4.8K and -$7K
  • B-$4.9K and $7K
  • C$4.8K and -$7K
  • D$4.8K and $7K

Unlock PK0-004 to see the answer

You've previewed enough free PK0-004 questions. Unlock PK0-004 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PK0-004 Practice
A sponsor requests that the project team shorten the completion of... | PK0-004 Q#201 Answer | NerdExam