nerdexam
CompTIA

PK0-004 · Question #201

A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is…

The correct answer is C. $4.8K and -$7K. Cost Variance = EV - AC 30000 - 25200 = 4800 30000 - 37200 = -7200

Project management concepts

Question

A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000. Which of the following represents the cost variance for both project completions?

Options

  • A-$4.8K and -$7K
  • B-$4.9K and $7K
  • C$4.8K and -$7K
  • D$4.8K and $7K

How the community answered

(50 responses)
  • A
    10% (5)
  • B
    4% (2)
  • C
    64% (32)
  • D
    22% (11)

Explanation

Cost Variance = EV - AC 30000 - 25200 = 4800 30000 - 37200 = -7200

Topics

#earned value management#cost variance#EVM calculation#schedule compression

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice