A project manager is not required to participate in performance appraisal meetings with team members. The project manager is working within which of the following organizational structures?
The correct answer is C. Functional. In strong matrix organizations, the project manager has the authority and a full-time role. This structure has the characteristics of a projectized organization. The functional manager has a minimal role in a strong matrix organization.
Question
A project manager is not required to participate in performance appraisal meetings with team members. The project manager is working within which of the following organizational structures?
Options
- AProjectized
- BBalanced matrix
- CFunctional
- DStrong matrix
How the community answered
(33 responses)- A3% (1)
- C94% (31)
- D3% (1)
Explanation
In strong matrix organizations, the project manager has the authority and a full-time role. This structure has the characteristics of a projectized organization. The functional manager has a minimal role in a strong matrix organization.