Which of the following represents additional unauthorized requirements from the client?

The correct answer is A. Scope creep. Scope creep, due to the client asking for it, the scope is changing, gold plating is filling up time/resources without client awareness

Project management concepts

Question

Which of the following represents additional unauthorized requirements from the client?

Options

  • AScope creep
  • BChanging scope baseline
  • CChange request
  • DGold plating

How the community answered

(34 responses)
  • A
    88% (30)
  • B
    3% (1)
  • C
    3% (1)
  • D
    6% (2)

Explanation

Scope creep, due to the client asking for it, the scope is changing, gold plating is filling up time/resources without client awareness

Topics

#scope creep#scope management#unauthorized requirements#change control