CompTIA
PK0-004 · Question #250
PK0-004 Question #250: Real Exam Question with Answer & Explanation
Sign in or unlock PK0-004 to reveal the answer and full explanation for question #250. The question stem and answer options stay visible for context.
Question
A status report shows that the earned value is $50,000, the planned value is $40,000, and actual costs are $45,000. Which of the following is the SPI of the project, and is the project ahead or behind schedule?
Options
- ASPI = 0.89, ahead of schedule
- BSPI = 0.90, behind schedule
- CSPI = 1.11, behind schedule
- DSPI = 1.20, ahead of schedule
Unlock PK0-004 to see the answer
You've previewed enough free PK0-004 questions. Unlock PK0-004 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.