PK0-004 · Question #233
Which of the following risk strategies prevents a risk from impacting a project?
The correct answer is C. Avoid risk. Risk avoidance eliminates the threat entirely by changing the project plan, making it the only strategy that prevents a risk from impacting the project.
Question
Which of the following risk strategies prevents a risk from impacting a project?
Exhibit
Options
- AAccept risk
- BMitigate risk
- CAvoid risk
- DTransfer risk
How the community answered
(44 responses)- A5% (2)
- B7% (3)
- C86% (38)
- D2% (1)
Why each option
Risk avoidance eliminates the threat entirely by changing the project plan, making it the only strategy that prevents a risk from impacting the project.
Accepting risk means the team acknowledges the risk exists and takes no proactive action, leaving the project fully exposed to its impact if it materializes.
Mitigating risk reduces the probability or impact of a risk but does not eliminate the risk, meaning it can still affect the project.
Avoiding a risk means altering the project plan to eliminate the risk trigger altogether - such as removing a risky activity, changing scope, or extending the schedule - so the risk event cannot occur and therefore cannot impact the project. Unlike other strategies, avoidance is the only approach that fully prevents impact rather than reducing, shifting, or absorbing it.
Transferring risk shifts the financial or operational burden to a third party such as through insurance or outsourcing, but the risk event itself can still occur and disrupt the project.
Concept tested: Risk response strategies - avoidance vs. other approaches