PK0-004 · Question #232

A key stakeholder asks the project manager for additional features. Which of the following documents should the project manager refer to before responding to this request?

The correct answer is B. Change control plan. Before responding to a stakeholder's request for additional features, the project manager must consult the change control plan to understand the formal process governing how scope changes are requested and approved.

Tools and documentation

Question

A key stakeholder asks the project manager for additional features. Which of the following documents should the project manager refer to before responding to this request?

Options

  • AProcess diagram
  • BChange control plan
  • CBalanced scorecard
  • DSWOT matrix

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    91% (21)
  • D
    4% (1)

Why each option

Before responding to a stakeholder's request for additional features, the project manager must consult the change control plan to understand the formal process governing how scope changes are requested and approved.

AProcess diagram

A process diagram illustrates workflow steps visually but does not define the governance procedures for approving or rejecting scope change requests.

BChange control planCorrect

The change control plan defines the procedures, roles, thresholds, and approval workflows for submitting and evaluating project scope changes. Referring to it ensures the project manager communicates the correct process to the stakeholder, maintains scope integrity, and avoids making informal commitments that bypass governance controls.

CBalanced scorecard

A balanced scorecard is a strategic performance management tool used to track organizational objectives and is not applicable to managing individual project change requests.

DSWOT matrix

A SWOT matrix analyzes strengths, weaknesses, opportunities, and threats at a strategic or situational level and has no role in governing project scope change requests.

Concept tested: Change control plan governing stakeholder scope change requests

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#change control#scope management#stakeholder management#change request