PK0-004 · Question #231
A project manager wants to ensure that a detailed overview of a new kitchen fits the client's standards. Which of the following will the project manager MOST likely work to accomplish?
The correct answer is B. Gate reviews to capture the progress and feedback. Gate reviews are structured checkpoints where deliverables are evaluated against the client's standards and feedback is captured before the project advances to the next phase.
Question
A project manager wants to ensure that a detailed overview of a new kitchen fits the client's standards. Which of the following will the project manager MOST likely work to accomplish?
Options
- ADetailed project schedule to deliver on time
- BGate reviews to capture the progress and feedback
- CReasonable number of changes to maintain quality
- DWide range of time between the start and end of the installation
How the community answered
(36 responses)- A3% (1)
- B81% (29)
- C6% (2)
- D11% (4)
Why each option
Gate reviews are structured checkpoints where deliverables are evaluated against the client's standards and feedback is captured before the project advances to the next phase.
A detailed project schedule manages delivery timing but does not provide a mechanism for the client to review deliverables and verify they meet their standards.
Gate reviews (phase-gate reviews) allow the project manager and client to formally assess whether work completed so far - such as a detailed kitchen overview - meets defined standards and expectations. They create an explicit opportunity to capture client feedback and make corrections before proceeding, directly ensuring the deliverable aligns with client standards throughout the project lifecycle.
Limiting the number of changes helps preserve quality stability but does not create a structured review process through which the client can validate standards are being met.
A wide time range between start and end relates to scheduling flexibility or float, not to a structured quality review against client standards.
Concept tested: Phase gate reviews for client quality and feedback validation
Source: https://www.pmi.org/learning/library/phase-gate-review-process-5902
Topics
Community Discussion
No community discussion yet for this question.