PK0-004 · Question #241
Before a team can start on a sprint, they will need to:
The correct answer is C. review the backlog of work items to prioritize. In Agile Scrum, the team must review and prioritize the product backlog during sprint planning before committing to work items for the upcoming sprint.
Question
Before a team can start on a sprint, they will need to:
Options
- Acreate a set of iterations to work on and prioritize.
- Bgenerate an icebox of work items to review.
- Creview the backlog of work items to prioritize.
- Dtake client requirements and draft them into a task list.
How the community answered
(14 responses)- B7% (1)
- C93% (13)
Why each option
In Agile Scrum, the team must review and prioritize the product backlog during sprint planning before committing to work items for the upcoming sprint.
Creating a set of iterations describes higher-level release planning activities, not the immediate prerequisite step before starting an individual sprint.
An icebox holds deprioritized or deferred items and reviewing it is not a standard Scrum prerequisite before beginning a sprint.
Sprint planning requires the team to review the product backlog - an ordered list of all pending work items - and select the highest-priority items to commit to for the sprint. This prioritization step ensures the team focuses on the most valuable work and has a clear, agreed-upon sprint goal before development begins.
Converting client requirements into a task list is an earlier discovery or backlog creation activity that occurs well before individual sprint planning sessions.
Concept tested: Agile sprint planning and backlog prioritization
Source: https://scrumguides.org/scrum-guide.html#sprint-planning