PK0-004 · Question #242

A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date…

The correct answer is A. Revise the project plan. When a critical path task is at risk and the completion date and quality are fixed constraints, the project manager must first revise the project plan to identify a viable corrective action before any other steps.

Project management concepts

Question

A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?

Options

  • ARevise the project plan.
  • BUpdate the issue log.
  • CRequest additional funding.
  • DIssue a change request.

How the community answered

(30 responses)
  • A
    67% (20)
  • B
    10% (3)
  • C
    20% (6)
  • D
    3% (1)

Why each option

When a critical path task is at risk and the completion date and quality are fixed constraints, the project manager must first revise the project plan to identify a viable corrective action before any other steps.

ARevise the project plan.Correct

Revising the project plan is the necessary first step because it allows the project manager to identify schedule recovery techniques - such as fast-tracking or crashing - that can restore the timeline within the fixed constraints. Without a revised plan, the project manager has no concrete basis for requesting resources, communicating impacts to stakeholders, or formally issuing a change request.

BUpdate the issue log.

Updating the issue log documents the problem but does not produce a corrective action plan, making it a secondary recording activity rather than the next logical step.

CRequest additional funding.

Requesting additional funding assumes a specific solution and cannot be justified until the revised plan identifies whether increased costs are actually required to recover the schedule.

DIssue a change request.

Issuing a change request is a formal process that comes after the project manager has revised the plan and determined what specific changes to scope, schedule, or cost are needed.

Concept tested: Critical path corrective action and schedule recovery planning

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#critical path#corrective action#schedule management#project planning