PK0-004 · Question #242
A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date…
The correct answer is A. Revise the project plan. When a critical path task is at risk and the completion date and quality are fixed constraints, the project manager must first revise the project plan to identify a viable corrective action before any other steps.
Question
A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?
Options
- ARevise the project plan.
- BUpdate the issue log.
- CRequest additional funding.
- DIssue a change request.
How the community answered
(30 responses)- A67% (20)
- B10% (3)
- C20% (6)
- D3% (1)
Why each option
When a critical path task is at risk and the completion date and quality are fixed constraints, the project manager must first revise the project plan to identify a viable corrective action before any other steps.
Revising the project plan is the necessary first step because it allows the project manager to identify schedule recovery techniques - such as fast-tracking or crashing - that can restore the timeline within the fixed constraints. Without a revised plan, the project manager has no concrete basis for requesting resources, communicating impacts to stakeholders, or formally issuing a change request.
Updating the issue log documents the problem but does not produce a corrective action plan, making it a secondary recording activity rather than the next logical step.
Requesting additional funding assumes a specific solution and cannot be justified until the revised plan identifies whether increased costs are actually required to recover the schedule.
Issuing a change request is a formal process that comes after the project manager has revised the plan and determined what specific changes to scope, schedule, or cost are needed.
Concept tested: Critical path corrective action and schedule recovery planning