A project manager is mapping qualifications and available personnel to the project requirements. Which of the following activities is the project manager completing?

The correct answer is B. Team Selection. A project is represented by the individuals on the team, and ensuring the correct skills, level of experience, availability, and interest are all part of the team selection process.

Project management concepts

Question

A project manager is mapping qualifications and available personnel to the project requirements. Which of the following activities is the project manager completing?

Options

  • ATeam Building
  • BTeam Selection
  • CResource loading
  • DResource leveling

How the community answered

(59 responses)
  • A
    3% (2)
  • B
    90% (53)
  • C
    2% (1)
  • D
    5% (3)

Explanation

A project is represented by the individuals on the team, and ensuring the correct skills, level of experience, availability, and interest are all part of the team selection process.

Topics

#team selection#resource management#staffing#personnel planning