PK0-004 · Question #247
A change is being implemented on a project, and while in testing, it becomes clear that the change cannot be finalized due to the severe impact it would have on other critical systems. Which of the…
The correct answer is B. Regression plan. Regression analysis technique analyzes the interrelationships between different project variables.
Tools and documentation
Question
A change is being implemented on a project, and while in testing, it becomes clear that the change cannot be finalized due to the severe impact it would have on other critical systems. Which of the following should the team consult to determine which actions to take?
Options
- AIncident response plan
- BRegression plan
- CProgress plan
- DBusiness continuity plan
How the community answered
(64 responses)- A3% (2)
- B84% (54)
- C3% (2)
- D9% (6)
Explanation
Regression analysis technique analyzes the interrelationships between different project variables.
Topics
#regression plan#change management#impact analysis#testing