PK0-004 · Question #222

A project manager receives a call from the area regional building department and is informed that, upon inspection, waterlines from public water access to the project building do not meet local…

The correct answer is C. Gate. A gate (phase-gate) is a mandatory checkpoint where defined criteria - including regulatory compliance - must be satisfied before the project proceeds, and failing a building code inspection represents an unmet gate requirement.

Project life cycle phases

Question

A project manager receives a call from the area regional building department and is informed that, upon inspection, waterlines from public water access to the project building do not meet local material and installation code specifications. Which of the following items BEST describes the unmet objective?

Options

  • ASchedule
  • BMilestone
  • CGate
  • DTask

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    87% (26)
  • D
    7% (2)

Why each option

A gate (phase-gate) is a mandatory checkpoint where defined criteria - including regulatory compliance - must be satisfied before the project proceeds, and failing a building code inspection represents an unmet gate requirement.

ASchedule

Schedule refers to the planned timeline and sequencing of project activities and is unrelated to the regulatory compliance deficiency identified during the inspection.

BMilestone

A milestone marks the completion of a significant deliverable or project event and does not function as a pass or fail compliance checkpoint.

CGateCorrect

A gate is a formal review and decision checkpoint in the project lifecycle where specific pass or fail criteria, including compliance with local regulations and building codes, must be verified before work advances. The building department's finding that waterlines do not meet local material and installation code specifications means the project has failed a mandatory gate criterion. Regulatory inspection compliance is a classic gate requirement because failure blocks project progression until the issue is resolved.

DTask

A task is an individual unit of work assigned to a team member and does not represent a decision point or compliance verification requirement.

Concept tested: Phase-gate criteria and regulatory compliance checkpoints