PK0-004 · Question #203
A new stakeholder has requested the status and progress reports for the project milestones. Which of the following documents should the project manager address FIRST?
The correct answer is C. Project management plan. Before responding to any new stakeholder request, the project manager must first consult the project management plan, which defines all governance including how communications are handled.
Question
Options
- AProject communication plan
- BProject status report
- CProject management plan
- DProject backlog
How the community answered
(44 responses)- A2% (1)
- B5% (2)
- C91% (40)
- D2% (1)
Why each option
Before responding to any new stakeholder request, the project manager must first consult the project management plan, which defines all governance including how communications are handled.
The communication plan is a subsidiary of the project management plan; the PM should reference the parent document first to understand the full governance context.
A project status report is an output artifact, not a planning document - it cannot tell the PM how to handle a new stakeholder communication request.
The project management plan is the master governing document that contains or references all subsidiary plans, including the communications management plan. The PM must consult it first to understand what reporting cadence, format, and stakeholder access has already been established. Acting without checking this plan risks creating ad-hoc processes that conflict with approved project governance.
The project backlog is specific to Agile work tracking and does not govern stakeholder communication or reporting requirements.
Concept tested: Project management plan as governing document for stakeholder communication
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok