PK0-004 · Question #244

Which of the following defines the minimum level of engagement of a stakeholder?

The correct answer is A. Passive. Passive defines the minimum level of stakeholder engagement, representing a stakeholder who is aware of the project but takes no active role in it.

Project management concepts

Question

Which of the following defines the minimum level of engagement of a stakeholder?

Options

  • APassive
  • BInvested
  • CContributing
  • DInterested

How the community answered

(46 responses)
  • A
    87% (40)
  • B
    2% (1)
  • C
    7% (3)
  • D
    4% (2)

Why each option

Passive defines the minimum level of stakeholder engagement, representing a stakeholder who is aware of the project but takes no active role in it.

APassiveCorrect

In stakeholder engagement models used in project management frameworks, passive engagement is the baseline floor - the stakeholder has acknowledged awareness of the project but exerts no effort, provides no input, and takes no action. All higher engagement levels such as interested, contributing, or invested require progressively more active participation.

BInvested

Invested implies a stakeholder has committed resources, attention, or personal stake in the project outcome, which is a higher level of engagement than the minimum.

CContributing

Contributing means the stakeholder is actively providing work, information, or resources, placing them well above the minimum engagement threshold.

DInterested

Interested indicates the stakeholder is paying attention and seeking information about the project, which is still a step above purely passive awareness.

Concept tested: Stakeholder engagement levels classification

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#stakeholder engagement#engagement levels#stakeholder management