PK0-004 · Question #244
Which of the following defines the minimum level of engagement of a stakeholder?
The correct answer is A. Passive. Passive defines the minimum level of stakeholder engagement, representing a stakeholder who is aware of the project but takes no active role in it.
Question
Which of the following defines the minimum level of engagement of a stakeholder?
Options
- APassive
- BInvested
- CContributing
- DInterested
How the community answered
(46 responses)- A87% (40)
- B2% (1)
- C7% (3)
- D4% (2)
Why each option
Passive defines the minimum level of stakeholder engagement, representing a stakeholder who is aware of the project but takes no active role in it.
In stakeholder engagement models used in project management frameworks, passive engagement is the baseline floor - the stakeholder has acknowledged awareness of the project but exerts no effort, provides no input, and takes no action. All higher engagement levels such as interested, contributing, or invested require progressively more active participation.
Invested implies a stakeholder has committed resources, attention, or personal stake in the project outcome, which is a higher level of engagement than the minimum.
Contributing means the stakeholder is actively providing work, information, or resources, placing them well above the minimum engagement threshold.
Interested indicates the stakeholder is paying attention and seeking information about the project, which is still a step above purely passive awareness.
Concept tested: Stakeholder engagement levels classification
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok