PK0-003 Practice Questions
501 real PK0-003 exam questions with expert-verified answers and explanations. Page 7 of 11.
- Question #301
When would a project manager have a closure meeting? (Select THREE).
- Question #302
Before a change request is presented to the change control board, which of the following should the project manager do?
- Question #303
Which of the following should a project manager do for a team member who does not speak the same language?
- Question #304
A project manager is completing a project schedule network diagram using boxes to represent the project activities that are connected by lines to show their dependencies. Which of...
- Question #305
A conflict has developed among two project team members. The project manager reiterates the areas of agreement and avoids the areas of disagreement. Which of the following BEST des...
- Question #306
Which of the following directly utilize the WBS? (Select TWO).
- Question #307
Click on the exhibit button. Which of the following is the critical path?
- Question #308
Click on the Exhibit button. Which of the following is the float of the path: start-A-D-end?
- Question #309
Which of the following is the BEST method to avoid staffing conflict between resource managers and project managers?
- Question #310
After a change control board meeting, which of the following actions should the project manager do NEXT?
- Question #311
A statement of work (SOW) has been heavily revised by the stakeholders. Which of the following should be implemented to make it easier to determine how many times the document has...
- Question #312
Which of the following human resource outputs would a project manager use to determine a team member's skills?
- Question #313
All of the following are characteristics of a project EXCEPT that it:
- Question #314
Which of the following techniques can a project manager use to assist with quality planning? (Select THREE).
- Question #315
Reviewing the results of a control chart, the project manager finds the production samples had results inside both the upper control limit and the lower control limit. Which of the...
- Question #316
A project manager has a project with staff in four different countries. When generating the resource management plan, which of the following should be considered FIRST?
- Question #317
An approved change request has delayed the project start date without modifying the completion date. The project sponsor has requested the project manager to pursue an option with...
- Question #318
The project manager has constructed a graphical chart categorically representing the frequency of each data occurrence. This is an example of which of the following tools?
- Question #319
The project office has created change request templates that must be used on any corporate project. Which of the following BEST describes this action?
- Question #320
The project manager has received an approved change request. Which of the following actions should the project manager take NEXT?
- Question #321
Which of the following MUST be clearly defined in a project charter?
- Question #322
Which of the following is the MAIN difference between an open-ended and a close-ended problem statement?
- Question #323
A project team member, Joe, has completed his project work. Although the project is not completed yet, Joe has been assigned by the PMO director to a new project. Which of the foll...
- Question #324
Which of the following is used to provide a functional description of the efforts which are required in order to accomplish a task?
- Question #325
A project manager is entering the list of a project's activities with their estimated begin and end time to visualize which activities overlap and when the project is scheduled to...
- Question #326
The project manager is sequencing a set of activities. They discover that some of the activities may or may not occur based on the outcome of other activities. Which of the followi...
- Question #327
Which of the following is the MAIN difference between bottom up and top down cost estimation?
- Question #328
Which of the following purchasing processes should a project team use to ensure that the work will be done per company specifications, while selecting the overall cheapest provider...
- Question #329
One of the MAIN purposes of a kick-off meeting is to:
- Question #330
After the ground breaking at a new construction site, the pile driving operation comes to a full stop due to the nature of the terrain. Which of the following is MOST likely to occ...
- Question #331
A new software solution is being deployed. The customer realizes that an important piece of the software must be purchased in order for the project to be successful. Which of the f...
- Question #332
While performing a scheduled walkthrough at a construction site, the customer points out a discrepancy. Which of the following is the FIRST step that should be taken before submitt...
- Question #333
A project team member has identified a required change to one of their assigned tasks. The change would alter the order in which other tasks must be completed. Which of the followi...
- Question #334
Additional company employees have been assigned to the project. Which of the following will be affected?
- Question #335
Which of the following is the project manager implementing when they allocate additional resources to a set of tasks that are in the critical path and are slowing down the project...
- Question #336
The project manager is reviewing the Pareto chart to identify if the life cycle of a deliverable is producing software bugs. Which of the following are represented in the chart? (S...
- Question #337
The project manager wants to report to the stakeholders to date project's cost performance. If the total of completed work to date is $200,000 and the actual cost is $210,000, whic...
- Question #338
Some of the stakeholders are losing interest in the project because of its length. Which of the following should the project manager implement in this situation?
- Question #339
A project's deliverable has been assigned to a team located in a different country. Although it is understood that daily reports are due by close of business every weekday, the ext...
- Question #340
Which of the following should be used when determining the details of a project component or scope entry?
- Question #341
During the course of a project, key stakeholders have requested new requirements after the business requirements document has already been signed off. Which of the following should...
- Question #342
Which of the following scheduling algorithms establishes floats, durations, and paths between work schedule activities?
- Question #343
A draft structure for a risk trackingsheet has been provided below: 1.Risk identifier 2.Risk status 3.Risk description 4.Mitigation steps 5.Mitigation status Which of the following...
- Question #344
Which of the following is BEST suited for assigning resources to WBS tasks?
- Question #345
Which of the following can be used as a quality metric when performing quality planning?
- Question #346
A change request has been identified and submitted to the Change Control Board for approval. After gaining approval, which of the following should occur NEXT?
- Question #347
Which of the following is the FIRST step in a proper change management procedure?
- Question #348
A stakeholder wants to add another requirement to the deliverable. Which of the following will the project manager do to determine the change's effect on the project?
- Question #349
A project team is ready to identify activities needed to accomplish the project. Which of the following needs to occur FIRST?
- Question #350
The MOST detailed component of the WBS is known as: