PK0-003 · Question #347
Which of the following is the FIRST step in a proper change management procedure?
The correct answer is D. Identify a change. The fundamental initial step in any change management procedure is to identify and formally acknowledge that a change is needed or has occurred.
Question
Which of the following is the FIRST step in a proper change management procedure?
Options
- ACoordinate with appropriate stakeholders
- BUpdate the project plan
- CPerform impact analysis
- DIdentify a change
How the community answered
(48 responses)- A2% (1)
- B4% (2)
- C8% (4)
- D85% (41)
Why each option
The fundamental initial step in any change management procedure is to identify and formally acknowledge that a change is needed or has occurred.
Coordinating with stakeholders occurs after a change has been identified and its impact assessed, to gather input or communicate decisions.
Updating the project plan is a later step, performed only after a change has been formally approved.
Performing impact analysis is a subsequent step that follows the identification of a change, to understand its potential effects before any decision is made.
Identifying a change is the absolute first step in a proper change management procedure, as it marks the recognition that an alteration to the project's baseline or plan is necessary. Without this initial identification, the subsequent steps of analysis, approval, and implementation cannot commence.
Concept tested: Change Management- Initial Step
Source: https://www.pmi.org/learning/library/project-change-management-process-6880