Which of the following is the FIRST step in a proper change management procedure?

The correct answer is D. Identify a change. The fundamental initial step in any change management procedure is to identify and formally acknowledge that a change is needed or has occurred.

Project management concepts

Question

Which of the following is the FIRST step in a proper change management procedure?

Options

  • ACoordinate with appropriate stakeholders
  • BUpdate the project plan
  • CPerform impact analysis
  • DIdentify a change

How the community answered

(48 responses)
  • A
    2% (1)
  • B
    4% (2)
  • C
    8% (4)
  • D
    85% (41)

Why each option

The fundamental initial step in any change management procedure is to identify and formally acknowledge that a change is needed or has occurred.

ACoordinate with appropriate stakeholders

Coordinating with stakeholders occurs after a change has been identified and its impact assessed, to gather input or communicate decisions.

BUpdate the project plan

Updating the project plan is a later step, performed only after a change has been formally approved.

CPerform impact analysis

Performing impact analysis is a subsequent step that follows the identification of a change, to understand its potential effects before any decision is made.

DIdentify a changeCorrect

Identifying a change is the absolute first step in a proper change management procedure, as it marks the recognition that an alteration to the project's baseline or plan is necessary. Without this initial identification, the subsequent steps of analysis, approval, and implementation cannot commence.

Concept tested: Change Management- Initial Step

Source: https://www.pmi.org/learning/library/project-change-management-process-6880