nerdexam
CompTIA

PK0-003 · Question #350

The MOST detailed component of the WBS is known as:

The correct answer is D. Awork package. The work package represents the lowest and most detailed level of the Work Breakdown Structure (WBS), providing a granular view of project deliverables.

Project management concepts

Question

The MOST detailed component of the WBS is known as:

Options

  • AAn activity
  • BAcost account
  • CAsub-phase
  • DAwork package

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    4% (1)
  • D
    93% (25)

Why each option

The work package represents the lowest and most detailed level of the Work Breakdown Structure (WBS), providing a granular view of project deliverables.

AAn activity

An activity is a specific task or action that is performed to produce a work package or deliverable, but it is not a WBS component itself; rather, it's derived from the work package.

BAcost account

A cost account is a control point in the project's accounting system used to measure performance against cost and schedule baselines, not a component of the WBS structure.

CAsub-phase

A sub-phase is a higher-level grouping of work within a project phase, less detailed than a work package.

DAwork packageCorrect

A work package is the lowest level within the WBS hierarchy, representing a measurable and manageable component of work that can be realistically assigned, estimated for cost and duration, and controlled. It defines the specific work to be performed to achieve a deliverable.

Concept tested: WBS decomposition levels - work package

Source: https://www.pmi.org/learning/library/project-management-work-breakdown-structure-6874

Topics

#Work Breakdown Structure#Work package#Project planning

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice