PK0-003 · Question #350
The MOST detailed component of the WBS is known as:
The correct answer is D. Awork package. The work package represents the lowest and most detailed level of the Work Breakdown Structure (WBS), providing a granular view of project deliverables.
Question
The MOST detailed component of the WBS is known as:
Options
- AAn activity
- BAcost account
- CAsub-phase
- DAwork package
How the community answered
(27 responses)- A4% (1)
- B4% (1)
- D93% (25)
Why each option
The work package represents the lowest and most detailed level of the Work Breakdown Structure (WBS), providing a granular view of project deliverables.
An activity is a specific task or action that is performed to produce a work package or deliverable, but it is not a WBS component itself; rather, it's derived from the work package.
A cost account is a control point in the project's accounting system used to measure performance against cost and schedule baselines, not a component of the WBS structure.
A sub-phase is a higher-level grouping of work within a project phase, less detailed than a work package.
A work package is the lowest level within the WBS hierarchy, representing a measurable and manageable component of work that can be realistically assigned, estimated for cost and duration, and controlled. It defines the specific work to be performed to achieve a deliverable.
Concept tested: WBS decomposition levels - work package