nerdexam
ExamsPK0-003Questions#351
CompTIA

PK0-003 · Question #351

PK0-003 Question #351: Real Exam Question with Answer & Explanation

Sign in or unlock PK0-003 to reveal the answer and full explanation for question #351. The question stem and answer options stay visible for context.

Question

As a result of changes in the economy, it has been communicated that the current costs for needed components have doubled from what was originally budgeted. If the procurement occurs, this would result in exceeding the cost baseline for the project. Which of the following actions should the project manager take?

Options

  • AEvaluate alternatives that could be used that would result in the same scope to be produced
  • BUse contingency funds to cover the procurement of the components
  • CCreate a change request to see if the baselines can be revised to incorporate the appropriate
  • DContact the customer to let them know that the costs will be higher, and await approval from the

Unlock PK0-003 to see the answer

You've previewed enough free PK0-003 questions. Unlock PK0-003 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PK0-003 Practice