nerdexam
CompTIA

PK0-003 · Question #349

A project team is ready to identify activities needed to accomplish the project. Which of the following needs to occur FIRST?

The correct answer is C. WBS. To effectively identify project activities, the project team must first establish the Work Breakdown Structure (WBS) to decompose the overall project scope.

Project management concepts

Question

A project team is ready to identify activities needed to accomplish the project. Which of the following needs to occur FIRST?

Options

  • APERT
  • BRBS
  • CWBS
  • DOBS

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    91% (20)

Why each option

To effectively identify project activities, the project team must first establish the Work Breakdown Structure (WBS) to decompose the overall project scope.

APERT

PERT (Program Evaluation and Review Technique) is a scheduling method used to analyze and represent tasks, which is applied after activities have been identified.

BRBS

RBS (Risk Breakdown Structure) is a hierarchical breakdown of potential risks, which is developed during risk management planning, typically after the scope is well-defined.

CWBSCorrect

The Work Breakdown Structure (WBS) is a foundational project management tool that hierarchically decomposes the total scope of work into manageable segments. It serves as the prerequisite for defining specific activities, estimating resources, and developing the project schedule.

DOBS

OBS (Organizational Breakdown Structure) defines the project's organizational hierarchy and reporting relationships, not the work activities themselves.

Concept tested: Project scope decomposition - WBS

Source: https://www.pmi.org/learning/library/project-management-work-breakdown-structure-6874

Topics

#Work Breakdown Structure#Activity definition#Project planning

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice