Question

The project manager is sequencing a set of activities. They discover that some of the activities may or may not occur based on the outcome of other activities. Which of the following is BEST suited in this situation to show the activities' logical relationship?

Options

  • AGantt
  • BADM
  • CCCB
  • DCCM

Unlock PK0-003 to see the answer