nerdexam
CompTIA

PK0-003 · Question #161

During project execution, the project manager would create:

The correct answer is B. Astatus report. During the execution phase of a project, the project manager primarily focuses on carrying out the project plan and communicating progress to stakeholders.

Project life cycle phases

Question

During project execution, the project manager would create:

Options

  • AAWBS
  • BAstatus report
  • CAn issue log
  • DArisk register

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    95% (19)

Why each option

During the execution phase of a project, the project manager primarily focuses on carrying out the project plan and communicating progress to stakeholders.

AAWBS

A Work Breakdown Structure (WBS) is developed during the planning phase to decompose project deliverables, not created during execution.

BAstatus reportCorrect

A status report is a key communication tool created regularly during project execution to inform stakeholders about the project's progress, accomplishments, issues, and upcoming activities, ensuring transparency and accountability.

CAn issue log

An issue log is maintained and updated throughout the project lifecycle as issues arise, but its initial creation and the act of logging issues are part of monitoring and controlling, not a primary creation output of the execution phase itself.

DArisk register

A risk register is initially created and populated during the planning phase and then updated and monitored, but its primary creation is not an execution phase activity.

Concept tested: Project execution phase outputs

Topics

#project execution#status report#project communication

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice