PK0-003 · Question #161
During project execution, the project manager would create:
The correct answer is B. Astatus report. During the execution phase of a project, the project manager primarily focuses on carrying out the project plan and communicating progress to stakeholders.
Question
During project execution, the project manager would create:
Options
- AAWBS
- BAstatus report
- CAn issue log
- DArisk register
How the community answered
(20 responses)- A5% (1)
- B95% (19)
Why each option
During the execution phase of a project, the project manager primarily focuses on carrying out the project plan and communicating progress to stakeholders.
A Work Breakdown Structure (WBS) is developed during the planning phase to decompose project deliverables, not created during execution.
A status report is a key communication tool created regularly during project execution to inform stakeholders about the project's progress, accomplishments, issues, and upcoming activities, ensuring transparency and accountability.
An issue log is maintained and updated throughout the project lifecycle as issues arise, but its initial creation and the act of logging issues are part of monitoring and controlling, not a primary creation output of the execution phase itself.
A risk register is initially created and populated during the planning phase and then updated and monitored, but its primary creation is not an execution phase activity.
Concept tested: Project execution phase outputs