PK0-003 · Question #369

During the execution phase of a project, a change request has been approved to add activities to the critical path without altering the schedule. Which of the following techniques will the project man

The correct answer is D. Fast tracking. To deliver a project on time despite adding new activities to the critical path, the project manager will most likely use a schedule compression technique.

Project life cycle phases

Question

During the execution phase of a project, a change request has been approved to add activities to the critical path without altering the schedule. Which of the following techniques will the project manager MOST likely use to deliver the project on time?

Options

  • ABottom-up estimating
  • BRolling wave planning
  • CResource leveling
  • DFast tracking

How the community answered

(34 responses)
  • A
    3% (1)
  • B
    15% (5)
  • C
    6% (2)
  • D
    76% (26)

Why each option

To deliver a project on time despite adding new activities to the critical path, the project manager will most likely use a schedule compression technique.

ABottom-up estimating

Bottom-up estimating is a cost or duration estimating technique that aggregates estimates from lower-level components, not a schedule compression technique.

BRolling wave planning

Rolling wave planning is an iterative planning technique that elaborates plans in detail for the near term, not a method to shorten a project schedule.

CResource leveling

Resource leveling is a technique used to optimize resource utilization, which often extends the project duration to avoid resource over-allocation, contrary to the goal of maintaining the schedule.

DFast trackingCorrect

Fast tracking is a schedule compression technique where activities that would typically be done in sequence are performed in parallel, or their phases are overlapped. This method aims to shorten the overall project duration, allowing the project to stay on schedule even with added work on the critical path by adjusting the sequence of tasks.

Concept tested: Project schedule compression techniques

Source: https://projectmanagement.com/blog/blog-post/schedule-compression-techniques-fast-tracking-and-crashing/