PK0-003 · Question #271
Which of the following would be found in a post-mortem analysis? (Select TWO).
The correct answer is A. Lessons Learned E. Reasons for early termination of the project. A post-mortem analysis, or project review, documents key insights and outcomes upon project completion or termination.
Question
Which of the following would be found in a post-mortem analysis? (Select TWO).
Options
- ALessons Learned
- BTransition Plan
- CProject sponsor signoff
- DMaintenance responsibilities
- EReasons for early termination of the project
How the community answered
(45 responses)- A93% (42)
- B4% (2)
- D2% (1)
Why each option
A post-mortem analysis, or project review, documents key insights and outcomes upon project completion or termination.
Lessons Learned are a core output of a post-mortem analysis, summarizing successes, failures, and recommendations for future projects to improve processes and avoid past mistakes.
A Transition Plan is prepared before project closure to guide the handover of deliverables, not as a component of the post-mortem analysis itself.
Project sponsor signoff typically occurs at project initiation (for the charter) and final acceptance, distinct from the analytical content of a post-mortem report.
Maintenance responsibilities are detailed in the transition plan and operational documentation, not typically as part of the post-mortem analysis report.
If a project is terminated prematurely, the post-mortem analysis thoroughly investigates and documents the specific reasons for its early cessation, providing critical insights for organizational learning and future decision-making.
Concept tested: Project closure activities - Post-mortem analysis