PK0-003 · Question #327
Which of the following is the MAIN difference between bottom up and top down cost estimation?
The correct answer is A. Bottom up leads to a more accurate cost estimate than top down because it is performed by. This question seeks the primary distinction and comparative accuracy between bottom-up and top-down cost estimation approaches in project management.
Question
Which of the following is the MAIN difference between bottom up and top down cost estimation?
Options
- ABottom up leads to a more accurate cost estimate than top down because it is performed by
- BTop down leads to a more accurate cost estimate because it is performed by upper management
- CBottom up leads to a less accurate cost estimate because it is breaks down the task into smaller
- DBoth top down and bottom up are equally accurate estimation of a project's total cost because
How the community answered
(60 responses)- A88% (53)
- B2% (1)
- C3% (2)
- D7% (4)
Why each option
This question seeks the primary distinction and comparative accuracy between bottom-up and top-down cost estimation approaches in project management.
Bottom-up estimation involves detailing all work packages, estimating their individual costs, and then summing them to get a total project cost, making it generally more accurate because it's based on detailed work breakdown and often estimated by those performing the work. This granular approach provides a more precise and defensible cost figure than high-level estimates.
Top-down estimation, while quicker and often performed by upper management based on historical data, is typically less accurate for detailed project planning due to its high-level nature and lack of granular detail.
Bottom-up estimation specifically breaks down tasks into smaller components to achieve greater accuracy, not less, by allowing for more precise cost calculations at a detailed level.
Top-down and bottom-up estimates are not equally accurate; bottom-up estimation is generally considered more accurate because it builds from detailed work packages.
Concept tested: Project cost estimation techniques
Topics
Community Discussion
No community discussion yet for this question.