PK0-003 · Question #162
Which of the following tasks are performed within the initiation phase?
The correct answer is D. Create a charter document. The initiation phase establishes the project's purpose and formal authorization, with the project charter being the key document that grants this authority.
Question
Which of the following tasks are performed within the initiation phase?
Options
- ACreate a WBS
- BCreate a budget
- CCreate a risk register
- DCreate a charter document
How the community answered
(22 responses)- B9% (2)
- C5% (1)
- D86% (19)
Why each option
The initiation phase establishes the project's purpose and formal authorization, with the project charter being the key document that grants this authority.
Creating a Work Breakdown Structure (WBS) is a detailed planning activity performed in the planning phase, not the initiation phase.
Creating a detailed budget is part of the planning phase, where resource costs are estimated and allocated, rather than the initiation phase.
Creating a risk register, which involves identifying and analyzing potential risks, is a key task performed during the planning phase, not the initiation phase.
Creating a project charter document is the primary deliverable of the initiation phase, as it formally authorizes the project, defines its high-level objectives, and assigns the project manager with the authority to apply organizational resources.
Concept tested: Project initiation phase deliverables