PK0-003 · Question #344

Which of the following is BEST suited for assigning resources to WBS tasks?

The correct answer is D. WBS defines activities and deliverables that can be mapped to functional teams. The Work Breakdown Structure (WBS) decomposes project work into activities and deliverables, making it ideal for assigning specific resources or functional teams to manageable work packages.

Project management concepts

Question

Which of the following is BEST suited for assigning resources to WBS tasks?

Options

  • AWBS defines functional teams which should then be mapped to project scope items
  • BWBS contains the project schedule which should be used to determine timing of when to engage
  • CWBS defines the description of the end result delivered by the project
  • DWBS defines activities and deliverables that can be mapped to functional teams

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    3% (1)
  • D
    88% (29)

Why each option

The Work Breakdown Structure (WBS) decomposes project work into activities and deliverables, making it ideal for assigning specific resources or functional teams to manageable work packages.

AWBS defines functional teams which should then be mapped to project scope items

The WBS primarily defines the scope and deliverables, not functional teams; mapping teams to scope items happens after the WBS defines those items.

BWBS contains the project schedule which should be used to determine timing of when to engage

While the WBS is a foundation for scheduling, it does not contain the project schedule; the schedule is developed from the WBS activities, and resource timing comes from the schedule.

CWBS defines the description of the end result delivered by the project

The WBS defines the components of the end result and the work required to produce them, not merely a high-level description of the end result itself, breaking down work into actionable items.

DWBS defines activities and deliverables that can be mapped to functional teamsCorrect

The Work Breakdown Structure (WBS) breaks down the total project scope into discrete, manageable activities and deliverables. This granular decomposition clearly defines the work packages, allowing project managers to effectively map and assign specific functional teams or individual resources with the necessary skills to each WBS element for execution.

Concept tested: Work Breakdown Structure (WBS) purpose

Topics

#Work Breakdown Structure#Resource allocation#Project planning#Deliverables